2 lanes of York Street closed until 2020 for PATH extension

Last Updated Jan 4, 2019 at 5:51 am EDT

The PATH extension will link 16 York St. to the ICE Condominium. HANDOUT/City of Toronto

Toronto’s underground PATH system is being extended under York Street, which means a portion of the roadway will be closed so that the work can be done.

Starting on Friday, one lane in each direction of York Street between Bremner Boulevard and Lake Shore Boulevard West will be closed until April 2020.

The PATH extension, which will link 16 York St. to the ICE Condominiums, south of Bremner, is expected to open in June of that year. See a map of the PATH here.

Work on the extension will be done from 7 a.m. to 11 p.m. Monday to Friday, and from 7 a.m. to 5 p.m. on Saturdays.

Work won’t take place on Sundays or statutory holidays.